Thanksgiving is approaching, and many plastics processors are preparing to shut down their machines for a few days.
But before you turn off the heaters and head home, there's one important question to consider: What happens to the resin left inside your equipment?
Leaving production resin in the barrel during an extended shutdown can lead to material degradation, carbon buildup, black specks, and difficult startups. Even after the heaters are turned off, the resin can remain hot enough to degrade as the equipment gradually cools.
Fortunately, properly purging and sealing your machines before shutdown can help prevent these problems and make restarting production much easier.
Here's what every injection molder and extruder should know before the holiday break.
1. Turning Off the Heaters Doesn't Immediately Stop Resin Degradation
One of the most common misconceptions about shutdowns is that turning off the barrel heaters immediately stops resin degradation.
Unfortunately, that's not how it works.
When the heaters are turned off, the screw, barrel, and surrounding components retain heat. Depending on the equipment and processing temperatures, it can take hours for the material inside to cool sufficiently.
During that time, residual resin can continue to degrade, particularly when exposed to oxygen.
As degradation progresses, the material may discolor, oxidize, and eventually form carbon deposits that adhere to internal metal surfaces.
Some resins are more sensitive to prolonged heat exposure than others. Engineering and high-temperature materials can present additional challenges depending on their processing requirements.
The bottom line? Shutting down the heaters doesn't necessarily prevent the material left in your machine from degrading.
2. Degraded Resin Can Create Problems When Production Restarts
The consequences of leaving resin in the barrel often become apparent when operators return from a long weekend.
The machine reaches its operating temperature, production begins, and suddenly there are black specks, brown streaks, or other signs of contamination in the parts.
These problems may result from degraded resin and carbon deposits that formed before or during the shutdown.
Once these deposits are disturbed, they can enter the material stream and continue contaminating production.
This can create several costly problems:
- Increased startup scrap: More material and parts may need to be discarded before production meets quality requirements.
- Longer startup times: Operators may spend additional time cleaning the machine instead of producing acceptable parts.
- Recurring contamination: Carbon deposits can remain inside the equipment and continue breaking loose during production.
- Additional maintenance: Severe contamination may require more extensive cleaning or mechanical maintenance.
What was supposed to be a routine restart after Thanksgiving can quickly turn into hours of troubleshooting.
Fortunately, many of these problems can be reduced with a better shutdown procedure.
3. How Does Sealing With a Purging Compound Help?
Sealing is a preventive purging technique designed to protect processing equipment during shutdowns and extended downtime.
Instead of leaving heat-sensitive production resin in the barrel, operators displace it with an appropriate, thermally stable purging compound.
Sealing with Asaclean® helps reduce resin degradation by replacing the production material and limiting oxygen exposure inside the equipment during shutdown.
When performed correctly, this approach offers several advantages:
- Helps reduce carbon buildup and black speck contamination.
- Limits the amount of degraded resin remaining inside the machine.
- Reduces the likelihood of difficult startups.
- Helps minimize unnecessary startup scrap and downtime.
- Supports more consistent production after extended breaks.
Asaclean® offers purging compounds suitable for different processing temperatures, resin types, and equipment configurations.
However, not every purging compound is appropriate for sealing.
For example, glass-filled Asaclean® grades should never be used for shutdown sealing. Selecting the correct grade is essential for protecting the equipment and achieving the desired results.
For more information, review our Shutdown & Sealing recommendations.
4. How Should You Prepare Your Machines for a Holiday Shutdown?
A successful shutdown starts with planning.
Whether your facility operates injection molding machines or extruders, following a consistent procedure can help prevent contamination and unnecessary downtime.
Before your next extended shutdown, consider these five steps.
Step 1: Review your production schedule.
Identify which machines will be shut down and how long they will remain idle. Pay particular attention to equipment processing heat-sensitive materials or resins that have historically caused contamination.
Step 2: Select the appropriate Asaclean® grade.
Choose a thermally stable purging compound recommended for your processing temperature, resin, and machine configuration. Consult an Asaclean® Purging Expert if you're unsure which grade is appropriate.
Step 3: Purge out the production resin.
Follow the recommended procedure for your machine and selected purging compound. The objective is to remove the production resin and existing contamination before sealing.
Step 4: Properly seal the equipment.
Leave the appropriate purging compound inside the equipment according to the recommended sealing procedure. The specific steps will vary between injection molding and extrusion applications.
Step 5: Document the shutdown procedure.
Make sure operators know which compound was used, what procedures were followed, and what steps will be required when production resumes.
For detailed, application-specific guidance, refer to Asaclean® Purging Instructions.
5. What Should You Do When Restarting Production?
A proper shutdown can make a significant difference when your team returns to work.
If the machine was sealed correctly, the restart process is generally more straightforward than trying to remove degraded production resin.
Operators should follow the recommended startup procedure for their equipment and sealing grade.
This typically involves bringing the equipment back to the appropriate operating temperature, allowing sufficient time for heating, and displacing the purging compound before resuming normal production.
The goal is to begin producing acceptable parts with less contamination, scrap, and unnecessary downtime.
Remember that startup procedures can vary depending on the machine, resin, and Asaclean® grade used.
Following the correct instructions is just as important during startup as it is during shutdown.
6. Don't Forget to Check Your Purging Compound Inventory Before Thanksgiving
Preparing your machines is only part of a successful holiday shutdown.
You also need to make sure you have enough purging compound available to complete the process.
Before your facility closes, ask yourself:
- Do we have enough Asaclean® to seal every machine scheduled for shutdown?
- Are we using the correct grades for our equipment and processing temperatures?
- Do our operators have the necessary shutdown and startup instructions?
- Have we accounted for our purging needs when production resumes?
- Do we need to place an additional order before the holiday?
Waiting until the last production shift to discover you're short on purging compound can create unnecessary complications.
Plan ahead and place your Asaclean® orders early to ensure your team has the materials needed before the holiday shutdown.
Frequently Asked Questions
Can resin degrade in the barrel after the heaters are turned off?
Yes. The barrel and screw retain heat after the heaters are turned off, allowing resin to remain at elevated temperatures as the equipment cools. Depending on the material and conditions, degradation can continue during this period.
Should you purge an injection molding machine before a holiday shutdown?
Yes. Purging and properly sealing an injection molding machine before an extended shutdown can help reduce resin degradation, carbon buildup, and contamination during the next startup.
Can you leave Asaclean® in the barrel during a shutdown?
Yes, certain thermally stable Asaclean® grades are suitable for sealing equipment during shutdowns. However, not every grade is appropriate. Always confirm the correct grade and procedure before sealing. Never use a glass-filled Asaclean® grade for shutdown sealing.
Should extruders be purged before extended shutdowns?
Yes. Extruders can also experience resin degradation and contamination during extended downtime. Using an appropriate purging compound and sealing procedure can help reduce these problems.
How can you reduce black specks after a holiday shutdown?
One of the best preventive approaches is to remove the production resin and seal the equipment with an appropriate, thermally stable purging compound before shutdown. This helps limit degradation and carbon buildup that can contribute to black speck contamination during startup.
Make Your Next Startup Easier With Asaclean®
The last thing your team needs after a holiday break is a difficult startup caused by degraded resin and contamination.
Proper shutdown and sealing procedures can help protect your equipment, reduce unnecessary scrap, and get production running more efficiently when your employees return.
Asaclean® Purging Compounds are designed to help injection molders and extruders improve cleaning performance, reduce downtime, and maintain more consistent processing conditions.
Preparing for your Thanksgiving shutdown?
Make sure your equipment is protected and your purging compound inventory is ready.
Order Asaclean® Before the Holiday
Need help selecting the right grade or establishing a shutdown procedure? Contact an Asaclean® Purging Expert to discuss your application and review our Shutdown & Sealing solutions.
We hope that you have a wonderful holiday weekend and a painless startup after your holiday shutdown!
Ready to reduce your production downtime to protect your profits? Learn more about how purging compounds and process efficiency work in tandem.
Yoko Tanaka is the Marketing Manager at Asaclean. She has been helping molders and extruders learn about Asaclean purging and how to improve their processes for the past eight years.